Bptp Park Elite Premium Construction Update

Bptp Park Elite Premium Construction work almost finished most of them tower already construction wise and other work type is complete.  For More information shown below how much work is complete or not tower wise:-

TOWER L  = Tower L all work completed and ready for possession.

TOWER M = Tower L all work completed and ready for possession.

TOWER N = Tower L all work completed and ready for possession.

TOWER H = Tower L all work completed and ready for possession.

TOWER J = 99% STONE/TILING WORKS COMPLETED • 99% INTERNAL

TOWER K = 99% STONE/TILING WORKS COMPLETED • 99% INTERNAL

TOWER A = 98% INTERNAL PLASTER WORKS COMPLETED • 9 UNITS IPS FLOORING WORKS IS BALANCE • 70% EXTERNAL

TOWER B = 99% BRICK WORKS COMPLETED • 98% INTERNAL PLASTER WORKS

TOWER C = 99% BRICK WORKS COMPLETED • 98% INTERNAL PLASTER WORKS

TOWER D = 98% BRICK WORKS COMPLETED • 95% INTERNAL PLASTER WORKS

TOWER E =  Tower L all work completed and ready for possession.

TOWER F =  Tower L all work completed and ready for possession.

TOWER G = IPS FLOORING COMPLETED EXCEPT 1 FLAT • 20% STONE/TILING WORKS

EWS =16 OUT OF 56 FLATS IPS FLOORING COMPLETED • 25% INTERNAL

VILLAS 1-8 = 85% INTERNAL PUTTY/PAINTING WORKS COMPLETED • 85% INTERNAL

VILLAS 9-19 = 95% INTERNAL PLASTER WORKS COMPLETED • 50% EXTERNAL

 

 